A development can appear viable on a spreadsheet long before a lender agrees to fund it. The difference is usually not the concept of the project, but the strength of its numbers, approvals, borrower position and exit strategy. This guide to development finance stages explains how funding typically progresses for Australian residential and commercial property developments, and where careful structuring matters most.
Development finance is not a standard home loan with a larger limit. Lenders assess each stage against changing risks: site acquisition, planning approval, construction delivery and the sale or refinance of completed stock. Understanding this sequence early can help developers protect their equity, manage cash flow and avoid delays when the project needs to move.
Guide to development finance stages
While every project is assessed on its own merits, most development funding follows a clear path. The lender, loan structure and evidence required may change at each point.
1. Site identification and feasibility
The finance process starts before an unconditional contract is signed. At this stage, the developer assesses whether the proposed site can support a commercially workable project. This means looking beyond the purchase price to account for stamp duty, consultant fees, demolition, authority contributions, construction costs, holding costs, interest, marketing, GST and contingency.
A credible feasibility study should show the total development cost, expected gross realisation value or GRV, estimated profit margin and the amount of equity required. Lenders will closely examine these figures later, so assumptions need to be realistic. An optimistic end value or an outdated build-rate estimate can undermine an otherwise sound application.
Early finance guidance can also clarify a practical acquisition budget. A site that looks affordable based on a high-leverage construction scenario may not be suitable if the likely lender requires more borrower contribution or stronger presales.
2. Land acquisition finance
Once a suitable site is secured, funding may be required for the purchase itself. Depending on the project, this could be a residential investment loan, a commercial facility, private funding or a development loan that incorporates the land purchase and future works.
The right approach depends on the status of the planning approval, the borrower’s experience and how soon construction is expected to commence. A site with an existing development approval may attract more favourable consideration than a speculative land purchase awaiting a planning outcome. Conversely, a conventional land facility can provide flexibility where the development design is still being refined.
At this point, the lender will consider the contract price, valuation, title, zoning, planning pathway, borrower income or asset position, and available security. They will also want to understand how the purchase debt will be repaid if the project does not proceed as planned. This is one reason development finance is assessed as much on the exit as on the build itself.
3. Development approval and pre-construction preparation
The period between acquisition and construction can be expensive. Interest, council rates, land tax, consultant costs and design changes continue while the development approval, or DA, is progressed. A realistic programme and sufficient holding-cost allowance are essential.
Before approving construction funding, a lender will generally require final plans, DA evidence, building contract details, a quantity surveyor’s report, updated feasibility, valuation and evidence of the developer’s contribution. For larger or more complex projects, they may also review the builder’s experience, financial strength and track record delivering comparable works.
Presales can become important at this stage, particularly for multi-unit, townhouse or apartment developments. They give the lender evidence of market demand and a clearer repayment path. However, presales are not simply a box-ticking exercise. Lenders may apply requirements around deposit size, contract quality, purchaser profile and the proportion of stock sold. A project with fewer presales may still be fundable, but it will usually need stronger equity, a lower loan-to-cost ratio or a compelling alternative exit.
4. Construction funding and progressive drawdowns
Construction finance is usually advanced in stages rather than paid as one lump sum. Following settlement of the land, funds are drawn progressively as work is completed. Common drawdown points include site preparation, slab, frame, lock-up, fixing and practical completion, although the schedule will reflect the building contract and project type.
Before each drawdown, the lender commonly relies on a quantity surveyor or valuer to confirm the work completed aligns with the amount requested. This protects both parties. The developer avoids drawing unnecessarily early and increasing interest costs, while the lender confirms that its security is improving as expected.
Cash flow discipline matters most during this phase. Cost overruns, weather delays, supply shortages and variations can quickly erode the contingency allowance. A fixed-price contract can reduce some construction risk, but it does not remove every exposure. Site conditions, authority requirements and purchaser changes can still affect the budget and timeline.
Developers should also understand whether interest is capitalised within the facility or needs to be serviced from external cash flow. Capitalised interest can preserve liquidity during the build, but it increases the total debt and must be allowed for in the feasibility. There is no universally better structure - it depends on the project margin, available cash reserves and intended exit.
5. Completion, sales and loan repayment
At practical completion, the focus shifts from delivery risk to exit execution. For a sell-down project, settlements from completed lots or dwellings are used to reduce or repay the development loan. The lender may release individual securities as sales settle, subject to agreed release prices.
If the strategy is to retain the completed assets, the development facility is typically refinanced into longer-term investment, commercial or residual stock finance. This refinance should not be treated as an afterthought. The completed valuation, rental income, borrower servicing position and remaining debt must support the new loan structure.
Unsold stock can create pressure where the development facility reaches its maturity date before every property has settled. A well-structured facility accounts for a reasonable sales period, but developers should not rely on an extension as their primary plan. A conservative valuation, measured pricing strategy and viable refinance option provide more control if sales take longer than forecast.
What lenders assess across each stage
Lender appetite differs, but the core assessment areas remain consistent. They include the developer’s relevant experience, equity contribution, project feasibility, location, quality of approvals, builder credentials, valuation, presales and exit strategy.
Loan-to-cost ratio and loan-to-GRV ratio are central measures. Loan-to-cost compares debt with the total anticipated cost of the project. Loan-to-GRV compares debt with the completed value. A proposal may satisfy one measure but not the other, which is why borrowing capacity cannot be judged from a single percentage.
Experience also carries weight. A first-time developer may still obtain funding, but the structure may need to be more conservative, with additional equity, a simpler project or support from experienced project partners. Established developers are not exempt from scrutiny either. A lender will assess whether their experience is genuinely relevant to the scale, location and asset class of the proposed development.
Preparing for a stronger finance application
The most effective applications tell a consistent commercial story. The purchase price, consultant reports, valuation, construction contract, feasibility and sales evidence should support each other. Gaps between these documents invite questions and can slow approval.
Before approaching lenders, organise a current feasibility model, project timeline, planning documentation, building contract or detailed cost plan, borrower financials, statement of assets and liabilities, and evidence of equity. Where presales are relevant, have executed contracts and deposit evidence ready. It is also sensible to model downside scenarios, including softer end values, higher build costs and longer selling periods.
A specialist finance adviser can help test the proposal against the expectations of different lender types before an application is submitted. This matters because a major bank, non-bank lender and private funder may each view the same project through a different risk lens. The lowest headline rate is not always the strongest outcome if the facility terms, drawdown process or maturity date do not suit the development programme.
The best time to structure development finance is when a site is still being assessed, not when construction is ready to start. A clear funding pathway gives you a more reliable basis for negotiating the purchase, committing capital and carrying the project through to its chosen exit.